Recommended Autoclave Maintenance Schedule
TEC’s Recommended Maintenance Schedule for all Autoclave systems.
Recommended Autoclave Maintenance Schedule
Door System | |
---|---|
Clean lower 1/3 of locking ring | Weekly |
Inspect door seal for fit in groove of the door | Weekly |
Inspect door seal for nicks, gouges or embedded debris | Weekly |
Inspect sliding surfaces & wedges for excessive wear & alignment | Weekly |
Inspect for operation, clean and lube lock ring & shell flange (SS30) | Monthly |
Check hydraulic pump reservoir fluid level | Every 2 Months |
Lubricate door wedges surfaces with SS30 | Every 3 Months |
Inspect heat seal & replace if required | Every 6 Months |
Clean and apply protectant to door seal | Every 6 Months |
Strip wedges & flanges of lubricant and re-lube with SS30 | Once a Year |
Inspect hydraulic lines, fittings and cylinder packing for leaks | Once a Year |
Check wear plates for gouging: indicates door out of alignment | Once a Year |
Door Mechanism Operation | |
Inspect Camroll assembly | Once a Year |
Inspect door interlock cylinder & micro-switch for proper operation | Monthly |
Perform a nondestructive examination (NDE) on the lugs, wedges and closure | Once a Year |
Pressure Vessel Safety | |
Check and verify all pressure safety interlocks are functioning as designed | Every 6 Months |
Back flush pressure sense line | Every 6 Months |
Activate Person-In-Clave Alarm & confirm operation | Every 6 Months |
Calibrate or replace relief valves | Once a Year |
Replace rupture disks | Once a Year |
Check and calibrate pressure in autoclave switch & interlocks | Once a Year |
Vessel Inspection | |
Inspect vessel and nozzles for cracking, surface pitting | Every 6 Months |
Inspect vessel for high surface operating temperature | Every 6 Months |
Perform a magnetic particle test of vessel and nozzles | Every 3 Years |
Inspect vessel for minimum thickness | Every 5 Years |
Fan and Drive System | |
Remove housing, check all bolts, piping & electrical connections | Once a Year |
Inspect and grease fan shaft, seal & drive bearing | Once a Year |
Inspect and drain bell housing | Weekly |
Inspect connection of fan wheel & motor shaft, tighten as required | Once a Year |
Inspect sheave guards, belt guards and motor seal linkage | Once a Year |
Electrically Heated Vessels | |
Check functionality and operation of contactors and SCR | Once a Year |
Check functionality and operation over-temperature controller | Once a Year |
Inspect all wires in MCC and clave leading to and from the heater | Once a Year |
Check all contactors, starters, & circuit breakers for proper operation | Once a Year |
Check all connections for tightness, including power source line | Once a Year |
Gas Fired Vessels | |
Check combustion chamber over-temperature controller | Once a Year |
Replace spark plug, adjust pilot and adjust low & high fire | Once a Year |
Check the high & low gas pressure switches | Once a Year |
Check gas supply, double block, proof of closure switches, and bleed valves | Once a Year |
Check the low combustion air pressure switch | Once a Year |
Check the UV flame scanner, simulate alarms and flame indicators | Once a Year |
Inspect operating condition and cleanliness of blowers | Once a Year |
Inspect condition and cleanliness of gas train and internals | Once a Year |
Inspect combustion heating coil for leakage | Once a Year |
Oxygen Analyzer | |
Calibrate analyzer & check operation | Every 6 Months |
Vacuum System | |
Inspect pump packing | Every 6 Months |
Vent receiver tank and drain condensation | Monthly |
Pneumatic Systems | |
Test clean and range adjust all I/P transducers | Every 6 Months |
Inspect and range adjust all pneumatic control valves | Every 6 Months |
Drain & adjust all instruments and valve air regulators | Every 2 Months |
Autoclave Interior | |
Clean debris from inside of vessel | Weekly |
Check the sheet metal screws for tightness and clean sheet metal | Every 3 Months |
Check bolts for tightness | Once a Year |
Cooling System | |
Inspect and replace worn fan belts | Every 6 Months |
Inspect cooling valve for leakage | Every 6 Months |
Drain tank and refill | Once a Year |
Motor Control Center | |
Check contactors, starters, & circuit breakers | Once a Year |
Verify that all contactors are tight, including the incoming power | Once a Year |
Part Monitoring Sensors | |
Calibrate all vacuum transducers | Once a Year |
Check vacuum system fittings for tightness and leaks | Every 6 Months |
Check system PID tuning and adjust if required | Every 6 Months |
About Thermal Equipment Co.
Over 55 Years of Autoclave Experience
TEC supplies any size aerospace quality Autoclave Systems - everything from a smaller lab-size system, to a 30 foot diameter system. No matter the size, each of our Autoclave systems goes through the same rigorous custom engineering process - resulting in a high-quality Autoclave that is built to your unique specifications.